ECNEC approves 8 projects with Tk 10,468.24cr

DHAKA, March 3, 2020 (BSS) – The Executive Committee of the National Economic Council (ECNEC) today approved a total of eight projects involving Taka 10,468.24 crore including a first revised project for constructing Bangabandhu Sheikh Mujib Railway Bridge over River Jamuna with an additional cost of Taka 7,046.88 crore.

The approval came from the 21st ECNEC meeting of the current fiscal year held at the NEC Conference Room in the city’s Sher-E-Bangla Nagar area with ECNEC Chairperson and Prime Minister Sheikh Hasina in the chair.

Briefing reporters after the meeting, Planning Minister MA Mannan said that a total of 8 projects were approved today involving an overall estimated cost of Taka 10,468.24 crore.

“Of the total project cost, Taka 5,964.74 crore will come from the government of Bangladesh portion, Taka 78.63 crore from the concerned organization’s own fund while the rest of Taka 4,424.87 crore from project assistance,” he added.

Mannan said of the approved eight projects, six are new while two others are revised projects.

The planning minister said Bangladesh Railway under the Ministry of Railways will implement the Bangabandhu Railway Bridge project by December 2025.

With the latest revision, the total cost for the project reached Taka 16,780.95 crore where the Japan International Cooperation Agency (JICA) will provide Taka 12,149.19 crore.

Mannan said this railway bridge project is a “star” project of the government and this dual gauge double track railway bridge would be constructed around 300 meters upstream of the existing Bangabandhu Bridge.

Planning Commission officials said that at present the potentials of rail freight transport with the neighboring countries could not be exploited properly with the existing Bangabandhu Bridge due to limited access load and speed limitations.

Under the circumstances, this dedicated railway bridge is being constructed over River Jamuna to meet the growing demand of national and sub-regional rail traffic.

The main project operations include construction of a 4.8 kilometer long dual gauge double track bridge, construction of a 7.6 kilometer long double line railway approach embankment, erection of 30.73 kilometer dual gauge railway track, construction of 16 railway approach viaducts, minor bridges and culverts, renovation and remodeling of Bangabandhu Bridge East and Bangabandhu Bridge West stations and yards.

The project operations also include construction of railway museum and ancillary infrastructures, conducting dredging at the approach channel and harbour of River Jamuna as well as strengthening river training on the both sides of the bridge.

Mannan said the project cost of the railway bridge has been increased following a study conducted by JICA to further strengthen this dedicated bridge.