8th span installed, over 1200 meter of Padma Bridge visible

540

MUNSHIGANJ, Feb 20, 2019 (BSS) – The eighth span of the 6.15-kilometre
long Padma Bridge was installed today on its 35th and 36th no pillars at
Jajira end in Shariatpur.

The 150-meter long ‘6E’ span was installed around 12.15 pm, making 1,200
meters of the main structure of the mega bridge visible.

A total of 1050 meters of the bridge were visible at Jajira point with the
installation of the seventh span and one was installed at Mawa point making
150 meters visible.

The “6E” span has been successfully placed on the pillars with the efforts
of local and foreign engineers.

Another new span titled ‘6-D’ is expected to be installed on the 34th and
35th pillars of the bridge at the Jajira end by March 10.

Earlier on October 14, 2018, Prime Minister Sheikh Hasina unveiled the name
plaque of Padma Bridge Toll Plaza at the Mawa end.

According to experts, the national economy is expected to witness 1.2
percent GDP growth rate, while 0.84 percent poverty will be reduced every
year after completion of the bridge to be built with an estimated cost of
Taka 30,193.39 crore.

The first span of the Padma Bridge was installed on September 30, 2017. The
second span was installed four months later on January 28, 2018 while the
third one was placed on March 11, after one and a half months.

The fourth span was positioned on May 13, after two months. After one month
and 16 days, the fifth span was installed on June 29 while the sixth one was
placed on January 23, 2019.

According to the engineers concerned, a total of 41 spans will be installed
on 42 concrete pillars to complete the bridge.