25th span of Padma Bridge installed

925

MUNSHIGANJ, Feb 21, 2020 (BSS) – The 25th span of the 6.15-kilometre long Padma Bridge was installed on the 29th and the 30th pillars at Jajira point in Shariatpur district this afternoon.

With the installation of the span, 3,750 meters of the main structure of
the mega bridge has become visible,” Deputy Assistant Engineer of the bridge
project Humayun Kabir told BSS here.

He also said installation of all 41 spans will be completed within next
July as three spans would be set up in a month.

Besides, the construction of 38 pillars has already been finished among 42
pillars.

Earlier on October 14, 2018, Prime Minister Sheikh Hasina unveiled the
name plaque of Padma Bridge at the Mawa end.

Along with the spans installation, construction work of roadway slabs and
railway slabs is also progressing simultaneously, the official added.